China Yangtze Power Co. Ltd. announced on July 4, 2024, its preliminary electricity generation and water inflow statistics for the half year of 2024. Gross electricity generation from its domestic cascade hydropower projects reached approximately 120.618 billion KWh for the first half of 2024, a 16.86% year-on-year increase, while Q2 2024 generation was 67.871 billion KWh, a 42.54% year-on-year decrease. For the half year, water inflow at Wudongde Reservoir was approximately 36.660 billion cubic metres, up 11.40% year-on-year, and at Three Gorges Reservoir was 147.941 billion cubic metres, up 19.67% year-on-year.
| Date | 4 Jul 2024 |
| Time | 10:18:52 |
| Category | Miscellaneous |
| ID | 1688V |
China Yangtze Power Co., Ltd.
Announcement on Electricity Generation in the half year of 2024
This announcement contains the English translation of the Chinese version of China Yangtze Power Co.,Ltd. Announcement on Electricity Generation in the half year of 2024 as published on the website of the Shanghai Stock Exchange, and is provided for your reference only. In case of discrepancy between the Chinese version and the English version, the Chinese version shall prevail.
According to the preliminary statistics of the Company, the total water inflow at the Wudongde Reservoir by the half year of 2024 reached approximately 36.660 billion cubic metres, representing a year-on-year increase of 11.40%, while the total water inflow at the Three Gorges Reservoir reached approximately 147.941 billion cubic metres, representing a year-on-year increase of 19.67%.
The gross electricity generation of the Company's domestic cascade hydropower projects was approximately 120.618 billion KWh in the half year of 2024, representing a year-on-year increase of 16.86%. Among them, The gross electricity generation of the Company's domestic cascade hydropower projects was approximately 67.871 billion KWh in 2024 Q2, representing a year-on-year decrease of 42.54%. The output of each power station is as follows:
|
Project Name |
2024 Q2 |
The first half year of 2024 |
||
|
Gross Electricity Generation (billion KWh) |
Year-on-year change(%) |
Gross Electricity Generation (billion KWh) |
Year-on-year change(%) |
|
|
Wudongde Project |
7.863 |
32.79 |
13.819 |
18.35 |
|
Baihetan Project |
11.283 |
45.88 |
22.021 |
3.43 |
|
Xiluodu Project |
13.449 |
69.16 |
25.620 |
21.58 |
|
Xiangjiaba Project |
7.927 |
57.31 |
14.363 |
10.91 |
|
Three Gorges Project |
22.196 |
32.27 |
36.211 |
25.36 |
|
Gezhouba Project |
5.154 |
23.02 |
8.585 |
16.98 |
|
Total |
67.871 |
42.54 |
120.618 |
16.86 |